Capital Recovery Fee
Fee Schedule
|
Meter Size In Inches
|
Rated Flow (gpm)
|
Capital Recovery Fee
|
County Collection Fee
|
Total Charges
|
|
5/8 & 3/4"
|
20
|
$1,397
|
$34.93
|
$1,431.93
|
|
1"
|
50
|
$3,492
|
$87.30
|
$3,579.30
|
|
1.5"
|
100
|
$6,985
|
$174.63
|
$ 7,159.63
|
|
2"
|
160
|
$11,176
|
$279.40
|
$ 11,455.40
|
|
3"
|
320
|
$22,352
|
$558.80
|
$22,910.80
|
|
4"
|
500
|
$34,925
|
$873.13
|
$35,798.13
|
|
6"
|
1,000
|
$69,850
|
$1,746.25
|
$71,596.25
|
|
8"
|
1,600
|
$111,760
|
$2,794.00
|
$ 114,554.00
|
|
10"
|
2,300
|
$160,655
|
$4,016.38
|
$164,671.38
|
|
12"
|
4,300
|
$300,355
|
$7,508.88
|
$307,863.88
|
|
Apartments, Condos and Duplexes (Per Unit)
|
70% of EDU 175 gpd
|
$978
|
$24.45
|
$1,002.45
|
The cost to provide additional capacity has been determined to be $5.5873 per gallon per day.
|